e8736cb010 chore: update meta/component-layer and meta/schema-layer status to completed 2026-05-21 21:07:22 +00:00
3b27ba7c1b chore: update task schema/graph-schemas status to completed 2026-05-21 21:07:08 +00:00
0d6657657e chore: update tasks analysis/type-compat and schema/graph-schemas status to completed 2026-05-21 21:06:58 +00:00
b6cb32da3a chore: update task component/map status to completed 2026-05-21 21:05:59 +00:00
9c92618292 chore: update task component/conditional status to completed 2026-05-21 21:05:48 +00:00
d7578994fb chore: update task analysis/defaults status to completed 2026-05-21 21:02:07 +00:00
cbd26688f8 chore: update task status to completed for component-operation, schema-edge-attrs 2026-05-21 20:59:52 +00:00
c1c1c012d4 chore: update task schema/node-attrs status to completed 2026-05-21 20:56:31 +00:00
b2691283a2 chore: update task setup/test-infrastructure status to completed 2026-05-21 20:53:14 +00:00
8c997433e2 chore: update task status to completed for component-sequential, error-hierarchy, schema-enums 2026-05-21 20:53:06 +00:00
5231522b5e chore: update task component/parallel status to completed 2026-05-21 20:49:47 +00:00
0886ba1f00 chore: update task setup/project-init status to completed 2026-05-21 20:46:56 +00:00
466b121f77 decompose architecture into 38 atomic tasks across 12 parallel generations
Decompose the reviewed architecture specs into taskgraph-managed tasks:
- 2 setup tasks (project init, test infrastructure)
- 4 schema tasks (enums, node attrs, edge attrs, graph schemas)
- 1 error hierarchy task
- 6 graph tasks (FlowGraph class, 3 construction paths, queries, validation)
- 5 analysis tasks (type-compat, build-type-edges, ordering, template-validation, defaults)
- 5 component tasks (Operation, Sequential, Parallel, Conditional, Map)
- 2 host config tasks (GraphologyHostConfig, ReactiveHostConfig)
- 4 reactive tasks (WorkflowRoot, node-status, max-concurrency, retry-semantics)
- 3 review tasks (foundation, reactive-and-hosts, complete-library)
- 5 meta cluster tasks (schema, graph, component, reactive, analysis layers)
- 1 API exports task

Validated with taskgraph: zero cycles, 38 tasks, 12 parallel generations.
Critical path: 12 tasks through reactive execution layer.
2026-05-21 20:24:44 +00:00